Rapid and fast chargers for Volkswagen UK’s ports and National PDI Centre

The Challenge

VW AG will introduce 50 battery electric and 30 hybrid models by 2025. Around 1 in 4 VW Group vehicles sold will be electric. ElectrAssure’s solution will enable Volkswagen to reliably process the electric vehicles passing through its ports and Pre Delivery Inspection (PDI) Centre for the UK market. The number will rise from just over 15,000 EVs in 2020 to over 79,000 in 2023.

The Solution

ElectrAssure successfully tendered for the EV charging infrastructure for Volkswagen UK’s three port terminals in Tynemouth, Grimsby, and Sheerness and for their national PDI Centre on the Isle of Sheppey.

ElectrAssure specified 4 x 100kW Delta Ultrafast Chargers (UFC) for the PDI Centre, each with two CCS cables, sharing the power between the two cables. ‘Dynamic Demand Controller’ (DDC) manages and balances the total load.

Alfen Eve chargers were specified for the ports with Alfen’s ‘Active Load Balancing’ to control the load. All chargers are managed by the Hubeleon chargepoint management system from our partners, Hangar-19.

The Outcome

The ElectrAssure EV charging solution delivers a robust, reliable charging solution that operates within the available capacity of the electrical system at all times and is also future-proofed for the dramatic increase in expected numbers of vehicles. ElectrAssure continues to provide annual preventative and call-fix maintenance services to ensure the very high levels of availability demanded by Volkswagen.

"Working with ElectrAssure has been a delight. They’ve been very proactive, they’ve kept us informed of what’s going on and they’ve delivered everything to time.”
Nick Byrne
Group Vehicle Planning and Logistics Manager
Volkswagen Group UK

Download Our Brochure

Our new brochure provides an emailable overview of our business and services, optimised for screen viewing.

Download Brochure

Some of our valued clients

BCA Logo

VW Logo

Keolis Amey Logo

Western Power Distribution Logo

National Grid Logo

News & Articles

Maintaining Service Levels in an EV World

Maintaining Service Levels in an EV World

In November 2021, Storm Arwen wreaked havoc on electricity supplies in the North of England and Southern Scotland. Thousands of consumers were left without power, many for several days, leaving the local electricity network operators unable to fulfil their committed service levels. How would you maintain the availability of key personnel and their vehicles to achieve committed service levels if their vehicles are electric?

Read More

UK car industry calls for EV charger targets

UK car industry calls for EV charger targets

Read More


Prime Minister announces electric vehicle revolution

Prime Minister announces electric vehicle revolution

Read More